GARY D. WITT, Judge.
Sherry Nance ("Sherry")
Larry worked for Maxon when he was injured on December 12, 1989. Larry operated a hand-held grinder to grind plastic telephone parts. After experiencing pain and discoloration of his hands, Larry was diagnosed with Raynaud's disease
In 1994, the parties jointly filed with the Commission an "Application For Commutation of Future Benefits and Approval of Lump Sum Payment" of Larry's future weekly PTD benefits. The application requested approval of a lump-sum amount pursuant to 287.530
In 2010, Maxon twice approached Larry about settling his future PTD weekly benefit payments by payment of a lump sum. In August 2010, after a thorough review of his medical records and condition, an analysis by a physician hired by Maxon determined that Larry had a life expectancy of thirteen years. On February 24, 2011 and May 6, 2011, Maxon offered to settle Larry's claim for a lump sum of $181,434.24.
In June, 2011, Larry was diagnosed with cancer, which was unrelated to his work-related medical condition. On August 31,
On October 27, 2011, a revised joint agreement entitled "Request to Commute Permanent Total Disability Payments into Lump Sum Award" was sent to the Commission by Maxon's counsel via overnight private delivery (FedEx).
Later, on the afternoon that the revised settlement agreement was sent by Maxon to the Commission, Larry died. The morning after his death, the agreement was received by the Commission and filed. On November 14, 2011, upon learning of Larry's death, Maxon filed a request to "Withdraw Request to Commute Permanent Total Disability Payments into Lump Sum Payment." In that request, Maxon notified the Commission of Larry's death and alleged that under the Workers' Compensation Law,
On February 2, 2012, the Commission entered an order denying the request to commute and denying Sherry's request to approve the settlement agreement. The Commission found that (1) under section 287.530, PTD benefits are to be commuted to present value, and (2) because of Larry's death, no future payments were due and therefore the present value of the future PTD benefits was zero. In so finding, the Commission reached the legal conclusion that "We cannot commute the
This Court must affirm the Commission's decision unless it is not authorized by law or supported by competent and substantial evidence on the whole record. MO. CONST. ART. V, SEC. 18. Section 287.495.1 provides that an appellate court reviews questions of law and that the Commission's decision should be modified, reversed, remanded, or set aside only if: (1) the Commission acted without or in excess of its powers; (2) the award was procured by fraud; (3) the facts found by the Commission do not support the award; or (4) there was not sufficient competent evidence in the record to warrant the making of the award. "Questions of law are reviewed de novo." Pierce v. BSC, Inc., 207 S.W.3d 619, 621 (Mo. banc 2006). This Court is not bound by the Commission's interpretation or application of the law; therefore, no deference is afforded the Commission's interpretation of a statute. White v. Univ. of Missouri, Kansas City, 375 S.W.3d 908, 910 (Mo.App. W.D.2012) (citations omitted).
"Worker's compensation law is entirely statutory, and when interpreting the law, we ascertain the intent of the legislature by considering the plain and ordinary meaning of the terms and, if possible, give effect to that intent." Honer v. Treasurer of State, 192 S.W.3d 526, 529 (Mo.App. E.D.2006) (citation omitted). Provisions of an entire legislative act should be construed together and, if reasonably possible, all of its provisions must be harmonized. Edwards v. Hyundai Motor Am., 163 S.W.3d 494, 497 (Mo.App. E.D.2005). The law favors a statutory interpretation that tends to avert an unreasonable result. Id.
In Point One, the question is whether the Commission erred in denying the parties' joint request to commute because it found that it had no legal authority to consider the joint settlement under section 287.390. In Point Two, the question is whether the Commission had authority to approve the commutation under section 287.530, when it determined the settlement amount exceeded the present value of the future payments. Point Three is made moot by our holding in Points One and Two. Because Points One and Two rely on the interpretation of two statutes, for reference, we set out both sections at the outset.
Section 287.390.1,
Section 287.530, relating to commuting compensation, states as follows:
In Point One, Nance argues that the Commission erred in its February 2, 2012 order by failing to exercise its authority to grant the October 28, 2011 joint Request to Commute Permanent Total Disability Payments Into a Lump Sum Payment because section 287.390.1, relating to compromise settlements, gives it authority to approve voluntary settlements entered into by the parties. Specifically, Nance argues that section 287.530 is the procedure for commutation of future PTD payments into a lump sum when that issue is contested by either party and that the parties to a dispute regarding the commutation of future PTD payments may settle their disagreement, which would place the settlement under the province of 287.390.
Maxon argues that the parties' settlement agreement
Maxon argues that section 287.390 is not applicable to the facts of this case, and that if it is, then the version of the statute in effect as of the date of the injury should be applied. As such, we first determine whether section 287.390 is applicable to the facts of this case and if so, which version of the statute is applicable. As set out above, under its express terms, parties may enter
Here, the settlement agreement did not purport to waive Larry's rights under the Workers' Compensation Law, nor is the agreement against the rights of the parties. It is thus not among those that cannot be approved. However, because it has not been approved by an ALJ or the Commission, it is not valid at this time. Conley v. Treasurer of Missouri, 999 S.W.2d 269, 274 (Mo.App. E.D.1999) (overruled on other grounds).
Based on the word "shall," we interpret the post-2005 version of section 287.390 to mean that the Commission does not have discretion to reject the parties' settlement agreement if it meets the three above requirements, unless it finds that the agreement was the result of undue influence or fraud or that the employee did not understand his or her rights and benefits or did not voluntarily agree to accept the terms of the agreement.
Maxon argues that, because the original claim in this matter was resolved in 1993 by a final and unappealed award from the Commission, the claim is final and not subject to change or amendment. Obviously, Maxon did not hold this belief when it filed an application to commute the award to a lump-sum payment in 1994, or when it approached Larry about such a commutation at least twice in 2010. Maxon argues, and the Commission found, that section 287.390 only applies to settlements of the original claim and not to settlements of a commutation of future PTD payments. Such argument is inconsistent with the plain language of section 287.390, which does not restrict itself to an original proceeding. The section specifically includes "any agreement of settlement or compromise of any dispute or claim for compensation" (emphasis added). If this section were only applicable to the settlement of an original claim, the language regarding "any dispute" would be superfluous. "[I]t is `presumed that the legislature did not insert idle verbiage or superfluous language in a statute.'" Hargis v. JLB Corp., 357 S.W.3d 574, 587 (Mo. banc 2011) (citations omitted).
The interpretation argued by Maxon is also inconsistent with prior case law addressing the term "claim" under section 287.390. Specifically, this Court has found that the interpretation of "claim" to include disputes resolved informally through settlement agreements is consistent with the use of the word "claim" in section 287.390. Grubbs v. Treasurer of Missouri, 298 S.W.3d 907, 911 (Mo.App. E.D.2009); Treasurer of Missouri v. Cook, 323 S.W.3d 105, 109 (Mo.App. W.D.2010).
Maxon correctly argues that the final award of the Commission is binding. "Under section 287.495, the final award of the Commission is conclusive and binding on the parties unless either party appeals the award to the appellate court within thirty days." Taylor v. Ballard R-II School Dist., 274 S.W.3d 629, 633 (Mo.App. W.D.2009). The Commission essentially
However, one exception to this general rule is found within section 287.470, which gives the Commission statutory authority to modify an award due to a change in the condition of the injured worker. Buescher v. Missouri Highway and Transp. Comm'n, 254 S.W.3d 105, 109, n. 6 (Mo. App. W.D.2008). The parties alleged in the original settlement that was submitted to the Commission that Larry's June of 2011 cancer diagnosis constituted a change in condition that gave the Commission authority to modify the final award in this case. However, in order to fall within the statute, the change in condition must be causally connected to the work-related injury. Bunker v. Rural Elec. Co-op., 46 S.W.3d 641, 646 (Mo.App. W.D.2001). Because there is no allegation that Larry's cancer diagnosis was related to his work-related injury, this exception is inapplicable.
Nonetheless, sections 287.530, 287.241 and 287.470 all establish statutory exceptions to the finality of an award and provide the Commission with the statutory authority to amend or change a final judgment in limited circumstances. With the ability to amend or change an award comes the ability of the parties to reach a settlement of the amendment or change, subject to the approval of the Commission under section 287.390. Roth v. J.J. Brouk & Co., 356 S.W.3d 786 (Mo.App. E.D.2011). Section 287.390 "requires agency approval of all types of settlements" not just settlements of the original claim. Id. at 788 (emphasis in original).
In this case, the applicable statute authorizing a change to a final award is section 287.530. This section provides that either party to a workers' compensation award may file an application with the Commission to commute the future disability benefits granted in a final award into a lump-sum payment. Once such an application is filed, upon notice to the other party, the Commission may hold a hearing to determine whether it should commute the future disability benefits granted in a final award and determine any applicable lump-sum amount. In contested cases, section 287.530 sets forth the issues the Commission must consider, under the facts presented, in determining whether to grant such a commutation and in determining the appropriate amount of the lump-sum payment. Without any agreement from Larry, Maxon could have filed with the Commission an application to amend or commute the future PTD payments into a lump sum, and, had it been able to meet its burden under the statute, the Commission would have had the authority to grant such a request without Larry's approval. Similarly, Larry could have applied, under the statute, to commute the future PTD payments into a lump sum without the consent or agreement of Maxon. Under either scenario, it would have been up to the proponent of the commutation to prove the elements set forth in the statute, and the Commission would have been required to follow the statutory guidelines in determining whether to approve the commutation and in determining the applicable lump-sum amount.
Point One is granted.
In Point Two, Nance argues that the Commission erred in denying the parties' joint request to commute because section 287.530 gave it express authority to grant the motion. The Commission denied the request because "the present value of future installments due under the award is zero" and the Commission "cannot commute the award for more than the present value of future installments." (Emphasis added).
Maxon argues that the Commission was correct in finding the present value of the future PTD payments to be zero and that the Commission lacked the authority to commute the payments for a lump sum that is either more or less than the present value of the future payments. Maxon argues that under 287.530 the Commission must determine the "commutable value"
Maxon's argument before this Court is completely inconsistent with the agreement it drafted, entered into and filed before the Commission. In the agreement for commutation of the award in this case, Maxon agreed to pay the lump sum of $181,434.24 as a commutation of the future PTD payments due under the award. This amount was equal to the total payment of the weekly benefits for a period of twenty-four years, which was not reduced to present value. However, Maxon's own medical expert's affidavit, attached to the agreement, showed that Larry had a life expectancy of only thirteen years. Further, the agreement noted that Larry's cancer diagnosis would further reduce his life expectancy below the thirteen years set forth in the agreement. Under Maxon's argument, the Commission would have been without authority to approve the agreement as submitted, even if Larry had survived, because the agreement was not for the "commutable value" of the future PTD payments but was for more than the present value of the future payments under the stipulated facts.
A careful reading of section 287.530 establishes that this section sets forth the method for the Commission to determine the "commutable value" of future payments and the considerations that the Commission must apply in determining whether to grant or deny a request for commutation in a contested case. However, where, as here, the parties have reached a settlement agreement as to
Maxon argues that the value of the future PTD payments became zero upon Larry's death because PTD payments terminate upon the death of the employee under section 287.200.2, which relates to the amount of PTD. However, Maxon cites no authority to support its assertion that the Commission loses authority to proceed with a commutation after an employee's death. This argument ignores the plain language of Section 287.530.1, which states in relevant part that compensation may be commuted
The plain language of the statute indicates that the statute anticipates and allows dependents of a deceased employee to proceed with a commutation. This grants the Commission the authority to proceed with a commutation after the death of the employee. Maxon acknowledged at oral argument that it was aware of no purpose for the language in the statute dealing with the dependants of a deceased employee absent the Commission's ability to proceed with the action after the employee's death. "Statutes should be construed in such a way as to avoid unreasonable or absurd results." Great Rivers Habitat Alliance v. City of St. Peters, 384 S.W.3d 279, 288 n. 7 (Mo. App. W.D.2012) (citation omitted). "An entire clause of the statute should not be relegated to the status of excess verbiage." Schoemehl v. Treasurer of State, 217 S.W.3d 900, 902 (Mo. banc 2007).
Here, the settlement agreement requesting a commutation was jointly filed, with all parties agreeing and stipulating that the present value of the future PTD benefits award was $181,434.24.
Once the Commission was presented with the parties' agreement, the Commission was bound by the authority granted it in section 287.390, which governs its consideration of voluntary settlements. As was noted above, the parties dispute which version of section 287.390 applies to this settlement agreement. If the amendment to the statute is substantive, then it cannot be applied retroactively; in that event, the Commission is bound to apply the statute in existence at the time of Larry's injury. Goad v. Treasurer of Missouri, 372 S.W.3d 1, 6-7 (Mo.App. W.D.2011). "For purposes of a retroactivity analysis, `substantive law relates to the
Here, the amendment in question alters the method by which the Commission approves a settlement. The underlying rights of the parties do not change, nor do the parameters of the settlement agreement change. In fact, the 2005 amendments to this section were in effect at the time the parties entered into the settlement agreement in this case. Because the parties' rights within the settlement agreement are not affected by the amendment to the statute, the 2005 amendment is procedural in nature and is applicable in this case.
As discussed supra, the current version of section 287.390.1 mandates through the use of the word "shall" that the Commission approve a voluntary settlement as long as (1) it is not the result of undue influence or fraud; (2) the employee understands his rights and benefits; and (3) the employee voluntarily agrees to accept the terms of the agreement.
The 2005 amendments to this statute had the effect of restricting the discretion of the Commission to reject a settlement agreement between the parties. Here, there are no facts, allegations or arguments that either party used undue influence or acted fraudulently with regard to reaching the settlement terms. Indeed, the parties obtained a life expectancy evaluation and agreed upon a settlement value that surpassed Larry's expected life. Larry evidenced that he understood and accepted his rights by signing the agreement. Further, there is no allegation or evidence that Larry was forced or coerced into accepting the terms of the agreement. Maxon was clearly aware that the agreement for a settlement amount of twenty-four years of payments far exceeded its doctor's opinion as to Larry's thirteen-year life expectancy, and Maxon was clearly aware that Larry had been diagnosed with Stage Four cancer and that this would further decrease his life expectancy. Larry did not conceal these facts from Maxon, as they were specifically set out in the settlement agreement that Maxon drafted and filed with the Commission. Maxon makes no argument that Nance fraudulently withheld his medical condition. The fact that, in hindsight, Maxon believes it reached a "bad deal" is not grounds for the Commission to reject the settlement agreement. Thus, pursuant to the restricted discretion under the amended section 287.390.1 and based on the factual stipulations and settlement agreement in this case, the Commission was without discretion to reject the parties' settlement agreement.
This Court must affirm the Commission's decision unless it is not authorized by law. This Court is not bound by the Commission's interpretation or application of the law; therefore, no deference is
Point Two is granted.
Based on our holding under Points One and Two, we do not need to reach Nance's Point Three.
Finally, based on Nance's success on appeal in this matter, Maxon's request for sanctions for frivolous appeal pursuant to Rule 84.19 is denied.
The decision of the Commission is reversed and the cause remanded to the Commission for its approval of the settlement agreement in this cause.
All concur.